Facebook Twitter
Website Forum Archive All

You are here:    Forum - Issues & Concerns - Temporary closure of Mill Road at Sydney Harrison House from 7th May

Temporary closure of Mill Road at Sydney Harrison House from 7th May

Residents should be aware that Thames Water has applied for a temporary road closure to apply to a section of Mill Road whilst new water connection works are carried out.


 


The temporary closure will operate from the 07/05/2019 to and including the 11/05/2019 (full closure 24 hours for each day).


 


Access will be maintained for emergency service vehicles and for those frontages within the closure area, subject to the progress of the works and liaison with the works supervisor. 

Posted by: David Bartholomew | 29/04/2019 5:21 pm

Thanks David...

Posted by: Christine Atkinson | 30/04/2019 10:39 am

My email is cpa1964@hotmail.com. I haven’t been out yet to notice a road closure? Where is it Joanne....

Posted by: Christine Atkinson | 30/04/2019 10:38 am

Christine, please let me have your email address and I will send you the detailed plan.

Posted by: David Bartholomew | 30/04/2019 10:30 am

Was the village aware of the proposed road closure taking place today?

Posted by: Joanne Stone | 30/04/2019 9:20 am

Hello David
Can you help with any more information around this please. Or a link/contact for me. We live behind the building site and our close is often difficult to access already with lorries, cars and vans parked all the way down it etc. It would be good to know exactly where the closure will be. I looked on the Thames Water planned works website but it doesn’t seem to be there.
https://inyourarea.thameswater.co.uk/work-in-your-area

Posted by: Christine Atkinson | 30/04/2019 8:28 am

Login to post a reply

You are here:    Forum - Issues & Concerns - Temporary closure of Mill Road at Sydney Harrison House from 7th May